Securing the EV grid following the Inflation Reduction Act

By Ethan Goldsmith, Partner at Keyframe Capital
Ethan Goldsmith, Partner at Keyframe Capital, provides critical analysis of the electric vehicle (EV) market and charging infrastructure potential

Op-ed contributed by Ethan Goldsmith, Partner at Keyframe Capital


The passage of the Inflation Reduction Act (IRA) was electrifying for the energy transition. The legislation’s record US$1.2tn in funding will encourage more renewable energy, carbon capture, hydrogen production, and turbocharge sales of commercial and personal electric vehicles (EVs). In going beyond EV tax credits to provide billions of dollars for the deployment of EV charging infrastructure, its message is clear: EVs are on the way, and they’ll need to charge.

At peak demand, a fleet of commercial vehicles can consume as much energy as a skyscraper. How will aging grid infrastructure handle the massive influx of electricity required to charge them? 

We know that electrical outlets fry when there is too much load, especially when the circuit doesn’t have a breaker. If you’ve ever had to make a trip to your breaker box after plugging in an appliance (say, a hair blower), you know what I mean. 

The same can be true of the grid. That’s why we’re hedging our excitement about this “high-voltage” event, fearing that IRA funding will short-circuit. Our electric grid is aging, under-resourced, and governed by complex regulatory bodies without mechanisms to move at the bill’s intended speed. We need to address these issues before to ensure that the IRA can put pedal to the metal.

Supporting EVs with ageing infrastructure

Generally speaking, electrical panels in your home need replacement every 25 to 40 years. Grid operators aren’t required to follow the same rules. Our existing transmission lines were designed in the 1950s for moving power from a small number of large, mostly coal-fired generators to a population that has since doubled. The average age of U.S. power lines is almost 50 years, with power transformers typically averaging 40 years. In addition, 90% of U.S. electricity flows through this aging equipment and onto at least 25-year-old distribution lines. Without a standard way to upgrade and expand this network, we can’t add enough renewable generation to charge the increase of EVs coming off production lines. 

A growing EV market 

In 2011, EVs made up just .001% of all new car sales. Ten years later, their share of new car sales had increased to 3%. It may not seem like much, but we’re approaching an inflection point of 5%. Between 2011 and 2021, the US built zero new transmission lines. By 2050, we must triple our transmission infrastructure to accommodate enough renewable generation to meet decarbonization goals, including increased EV charging. While the IRA allots up to US$3bn for transmission project development, it can take five to ten years to site, permit, and build new transmission projects. Similar to its EV provisions, this legislation sends a shock along an unprepared, under-resourced circuit. 

Interconnection stalls

More than 1,400 GW of generation, including at least 930 GW of wind and solar, is stalled in interconnection queues, awaiting the completion of utility impact studies. In 2021, the US installed just 37 GW of wind and solar. If we continue developing at this pace, we wouldn’t clear the existing queue for another 25 years—eight years past 2040 decarbonisation goals. The typical wait time from connection request to commercial operation has increased to 3.7 years for projects built from 2011 to 2021, up two years from projects built between 2000 to 2011. 

EV charging infrastructure projects can also expect to hear ‘hold music’. Interconnection alone for Level 2 chargers can range up to six months, while installers of DC fast chargers can expect to wait anywhere between six months and two years. Projects that need utility easements can typically add as much as another year onto that schedule. There simply aren’t enough dedicated utility staff for EV infrastructure projects, an issue that is compounded by a lack of clear interconnection processes and timelines for each step of the process. As we’ve written about before, vehicles are on the way — we don’t have time to wait.

The EV fleet conundrum

Let’s say you’re the operator of a 30-vehicle fleet. Utilities, like Pacific Gas & Electric (PG&E), recommend that you have one charger for each vehicle. When you bought property to park your fleet, you thought about highway access, but now you’re fueling your fleet with electricity, not diesel. Your fuel source is the power grid or on-site generation (solar panels). You’ll need to acquire the equipment to charge your fleet, then connect that equipment to either the grid, on-site generation, or both. The IRA has done you well in incentivizing your purchase of EVs and that equipment, but you’ll find your costs soar as time to build and operate your chargers increases because lead times for equipment will continue to lag alongside interconnection timelines.

If you’re that fleet operator, you might be starting to feel less than optimistic about the IRA’s ability to deliver on its promises. Don’t worry, it’s not 1879 - the solutions have already been invented.

It’s time to implement already-existing solutions for EVs

Our circuit breakers for this funding could look like some of the following:

  • First breaker: Utilities should increase staffing for interconnection studies. Grid operators from CAISO to MISO have lamented a lack of engineers who can actually perform interconnection studies. This shortage is the result of several factors, from poor retention to a lack of training, but it won’t be solved without dedicated resources.
  • Second breaker: Utilities should standardise generator interconnection procedures and costs. In 2003, FERC issued standard procedures and a standard agreement governing the interconnection of generators larger than 20 MW. The Commission is still reviewing the need for creating specific requirements for the interconnection of renewables to the grid. By limiting the variability in timelines for development, FERC could promote EV infrastructure development and start to help clear the interconnection queue. This might also help keep staffing costs lower. 
  • Third breaker: Utilities should launch EV infrastructure-specific programs responsible for publishing guidelines and supporting developers. While utilities have dedicated large sums of money, like Duke Energy’s US$100mn news last year, real help for developers might come in the form of clear interconnection timelines, permitting and easement support, and consultative utility staff. Southern California Edison, for example, has staff that works with customers on everything from site selection to hardware procurement and installation.
  • Fourth breaker: Capital providers need to get smarter and more flexible. A typical Venture Capital (VC) investment is characterised by short-term hockey stick growth from a handful of successful investments. However, infrastructure investments have a return profile that is focused on long-term, steady, fixed returns over generations. VCs aren’t deterred - in 2021, they poured US$18bn into EV startups. Instead of hockey sticks, investors will need to understand the kind of bespoke capital structuring needed to finance complex assets and interconnection costs, a rare expertise in capital markets, especially to take advantage of Investment Tax Credits (ITC) where applicable. 

We know what the breakers might look like. It’s time to get them installed and to get US$329bn in needed capital flowing.

About Ethan Goldsmith

Ethan Goldsmith is an Investment Partner at Keyframe. He firmly believes the future is electric, across all sectors of the built environment. His passion, however, is the electrification of transportation and the broader implications of vehicle electrification on the electrical grid and other aspects of the economy.

Ethan spent the early part of his career working with, and for, the companies driving the transition to electrified transportation. This includes stops working in consulting and working at Rivian Automotive. Ethan first worked as a consultant at Roland Berger supporting the firm’s clients, primarily incumbents in the automotive industry, assessing the implications of vehicle electrification on their businesses. Just before joining Keyframe, Ethan worked for Rivian Automotive, supporting the early development of their commercial strategy.

Ethan holds a Bachelor of Business Administration from the Steven M. Ross School of Business at the University of Michigan in Ann Arbor, MI.​​​​​​​

Share

Featured Articles

The Monta-CPI Partnership Enables Contactless Payments

Alok Dubey, Regional Director Strategic Sales, shares how Monta is empowering EV drivers & expanding EV charging options through its CPI partnership

EV Mobility, Inclusive Driving & Cybersecurity Regulations

Matthew Walker, of ABC Mobility Group & Mobility in Motion, explores the coming cybersecurity regulations & their impact on disabled drivers

bp pulse Acquires Ashford International Truckstop

bp pulse aims to advance the electrification of Heavy Goods Vehicles (HGVs) & has acquired Ashford International Truckstop in its mission to do this

Fiserv: Shifting Gears on Electric Vehicle Charging Payments

Charging & Infrastructure

ABB's Electrification Testing & Formula E Partnership

Sustainability

Blue Whale EV & Blink Lead Maryland's Electric Revolution

Charging & Infrastructure